|
Most viewed - Green House Motel |
Day 26 Roof739 viewsThe roof is almost finished with just a few small snags to tidy up. Remember that there are no drawings for this project and it's a question of make-it-up-as-you-go. It's also a training excercise for my workers. We still have a lot to do on the land including a frontage wall with gate and motel gatehouse at one end, and another gate with archway at the other end of the land, a large sala as a dining-room restaurant, a floating sala on the pond, and a meeting room/classroom on the field behind.jazzman
|
|
Bathroom wall tiles.684 viewsBeen trying for several days to get cheap tiles, but the prices seem to have gone up considerably since I built my house. I really wanted white, but I was not prepared to pay 160 baht / m2 or more for the cheapest plain white tiles I could find. I was able to negotiate 123 baht / m2 for 54 m2 of these very light green ones.
It is not necessary to render the walls first.jazzman
|
|
After612 viewsForeman's own initiative, and I must say, it looks quite neat. I would personally have mitered the fascia boards, but one can't expect everything, and this is a budget build after all.
I finally got the price of the plot of land down to one sixth of the Pattaya price. I still think I paid a bit over the odds, but it's really worth it to have a perfectly rectangular piece of land, and to avoid anyone building near my house.
jazzman
|
|
Ceiling suspension: strips606 viewsThe rails are suspended from the rafters or tile battens by aluminium strips.jazzman
|
|
Day 6 - The first walls .601 viewsOne lady mixing and passing up the bricks, one man bricking: Just 3 hours work for this much The others are preparing the 4" WC pipes and grey water pipes that will be under the floors - with five bathrooms, this is a bit more work than for the average house. Foreman thinks we'll have everything finished in 4 weeks. we'll see. We've been working together for three years now, and he and his family have almost become part of our family - grainjai permitting :)jazzman
|
|
Day 7599 viewsMost of the walls are built, except the font ones that will have the doors and windows. Still some steel to be put in the roof. The workers chop and change what they are doing, but I let them get on with it. I can watch everything from my office window only 20m away.jazzman
|
|
Day 3. Pre cast columns598 viewsExcept for one rough sketch, there are no drawings of any kind for this project. The day was spent digging out the rest of the footings, laying concrete and the the rebar. By the end of the day eight of the twelve columns had been erected. There will be four hotel rooms, and the extension (not visible), will be a decorative steel covered patio for the pool with WC & shower, and laundry room for the motel.
Completely up-to-date rebar prices hve been posted on the forum.jazzman
|
|
Day 5593 viewsHad some unusual rain in Isaan for 2 days so the time was spent painting the rest of the steel in the shed, getting a truck load of dirt delivered, and bending more braces.
The ground beams are poured and the roof steel half finished. I still never fathomed out why they have to use a platform to load the mixer. Notice the plastic bags round my expensive steel scaffolding to protect it from cement (a lesson learned from previous jobs).jazzman
|
|
Day 8587 viewsMore progress on the walls. The 7 cm thick concrete floors have been laid in three of the rooms and the pits for the septic tanks have been dug. Wire mesh reinforcing was laid in the concrete.jazzman
|
|
Septic tanks581 viewsDouble-chamber septic tanks with leech system. Our substrate is hard clay and does not percolate to allow seepage tanks. The two in the picture serve two rooms; there will be an identical installation at the other end of the building for the other two rooms and the outside WC/shower and laundry room. Black water flows into the first tank which overflows into the second tank. Grey water goes directly into the second tank. There are no kitchens so a grease trap is not required.jazzman
|
|
Chasing580 viewsThe electricians started today chasing the walls for the electrical conduits. Although this is a low budget build, we're still using relatively good quality fittings, and concealed wiring. I've tried many times to teach the men to cut the channels with an angle grinder and just knock out the the stuff in the middle, but to no avail. Still using a hammer and a bent nail. Back home in France I have a special two-bladed power tool attachment for doing this.jazzman
|
|
Cheap labour573 viewsFor all of those who are wondering why our labour bill of only 1,000 baht per square metre is so low...jazzman
|
|
44 files on 4 page(s) |
1 |
|
|
|
|
|