 Coolthaihouse Photo Gallery

Construction Photos
Home > House Construction > Cool Thai House Phase 2 > Roof

Most viewed - Roof
IMG_3420.jpg
Edge Tiles Replaced110 viewsThe edge tiles are replaced here without excess space between the tile edge and the fascia board. 2 commentsdozer
IMG_2020.jpg
Fascia100 viewsThis project used the heavier conwood (6" and 8") as fascia. This seems to work better than the thinner Shera fascia as the conwood doesn't warp over time.dozer
IMG_2116.jpg
Interior of Roof Structure99 viewsA shot of the interior of the roof structure with the tile battens in place.dozer
IMG_2135.jpg
Prefab Valley Material97 viewsThis is the chang prefabricated valley material as installed in a roof valley (shown from the inside). dozer
IMG_2121.jpg
Plastic Sheeting96 viewsPlastic sheeting is laid down no top of the 20 mm plywood walkway to protect it from rain.dozer
IMG_2169.jpg
Dry Tech96 viewsThe two layers of dry tech materials being set in place by the installer. dozer
IMG_1905.jpg
Post to be Topped Off95 viewsThis short post will be topped off with lanko 701 grout so the metal roof structure is sitting on concrete.dozer
IMG_2174.jpg
Dry Tech at the Ridge94 viewsThe dry tech along the ridge. There are two levels of material which sit on an aluminum rail. dozer
IMG_2176.jpg
Finished Roof Tiles94 viewsOne finished section of the roofing. Notice that the ridge tiles have not been affixed with any concrete per the dry tech method. dozer
IMG_2132.jpg
Lifting Tiles into Place93 viewsThe tile guys are lifting the tiles into place and setting them on the battens. dozer
IMG_2297.jpg
Bird Guard93 viewsThe bird guard is installed on the inside of the fascia board.dozer
IMG_2026.jpg
Double Box Sections92 viewsThe exterior of the roof structure was done with double box sections of 3.2mm 2x4.dozer
35 files on 3 page(s) 1