Inbound Water Test60 viewsDuring the inbound water pressure test the only place one should see any moisture is at the lids if they haven't be glued in place. dozer
IMG_1531.jpg
PVC Pipe Lids60 viewsAll PVC piping is covered to prevent concrete or other blockage from getting in it. Also the covers allow the inbound lines to be pressure tested. dozer
IMG_1896.jpg
Cementing the Shower Floor60 viewsLaying concrete in the shower floor area. Notice the rebar mesh in the other shower floor area. dozer
IMG_1488.jpg
Various PVC Pipes59 viewsShowing inbound water piping, a sink drain and vented toilet drain.dozer
BrKitchenLayout~0.JPG
Plan Bathroom + Kitchen Layout59 viewsThere are two bathrooms adjacent to each other. We continued the beam between the columns on the bathroom on the left for stability even though it is not shown in the plan.dozer
IMG_1492.jpg
Setting Toilet Drain56 viewsSetting the toilet at the correct distance per the plan. dozer
IMG_1491.jpg
Toilet Drain with Vent Opening55 viewsThe elbow has the all important vent opening which will be vented up through the roof and prevent sluggish toilet syndrome. dozer
IMG_1495.jpg
Drain Water Test55 viewsThe other end of the drain pipe is capped and tested for all drain pipes prior to pouring of any concrete. dozer
IMG_1480.jpg
Cutting Tool50 viewsThese cutting tools make it easy to get a nice cut on pvc. These are also required for cutting of the orange hot water flexi piping.dozer
IMG_1473.jpg
Vent Pipe Wired46 viewsA 3/4" vent pipe wired in place. dozer
   