|

Last additions - Cool Thai House Phase 2 |

Vent PipeThe 6 hun vent pipes to be extended up and routed through the specialty roof tiles which have an opening and plastic sleeve. dozerSep 26, 2011
|
|

Wall ShotThe walls are grooved for the vent pipes which will extend out through the roof. dozerSep 26, 2011
|
|

Vent PipesVend pipes extending upwards, eventually routed through the roof tiles. Venting into the attic space is not a good move as it creates a possible odor problem. dozerSep 26, 2011
|
|

Recessed Shower FlooringThe shower flooring is recessed to create a step down into the shower enclosure. dozerSep 26, 2011
|
|

Cementing the Shower FloorLaying concrete in the shower floor area. Notice the rebar mesh in the other shower floor area. dozerSep 26, 2011
|
|

Rough Bathroom LayoutsThe drain pipes for the floor drains are 3 inch, toilets are 4 inch, sinks are 1.5 inch. The purpose of the internal formwork is to later pour the shower floors since they will be a lower level. dozerSep 26, 2011
|
|

Bathroom LayoutBathroom nearing readiness to have the floors poured. The main floor will be poured first and then later the shower floors will be poured as they are at a lower level. dozerSep 26, 2011
|
|

Septic CoversScraping the bronze septic lids after the concrete walkway pour. dozerSep 26, 2011
|
|

6" Septic PVC Access and LidThe 6" Septic PVC access lid is covered in preparation for the walkway pour. Note the 6 hun vent pipe extending from the septic. It will be vented up through the wall and roof with the other vent pipes from the project. dozerSep 26, 2011
|
|

Preliminary Layout of Septic AccessAfter this we vented the septics and change the access lids to the 6" heavy duty type. dozerSep 26, 2011
|
|

Rough Plumbing LayoutAll of the inbound water pipes (1/2") and drain pipes ready for water pressure test. dozerSep 26, 2011
|
|

Setting Up the PumpBefore getting too far the pump needs to be set up for so the inbound lines can be pressure tested. Any problems can be checked/fixed before concrete is poured over any piping. dozerSep 26, 2011
|
|
437 files on 37 page(s) |
 |
 |
 |
 |
 |
25 |  |
 |
 |
 |
|

|
|
|