IMG_4043.JPG
Comparison Regular Cinderblock to Oversize CinderblockThis shows the size differential between the normal cinderblock and the oversize cinderblock. Please also note that the normal cinderblock generally has no openings at the bottom, where the oversize has standard size openings in the top and bottom.dozerSep 27, 2011
IMG_4045.JPG
Research - Color PigmentColoration of the render coat is impacted by a number of factors - the color of the fine aggregate sand use, the color of the cement, and the amount and ratios of pigment, cement, sand and water used. There several hundred test batches done to ensure the resultant color would match the design. This shows some test batches where color render was applied to cinderblocks.dozerSep 27, 2011
IMG_4040.JPG
Storage Room Midway through a ProjectThe storage room will reach maximum capacity about 1/2 way through any given project. The 1/2 way point is about the time the exterior roof is completed. After this some materials can be kept in the house.dozerSep 27, 2011
IMG_3060.JPG
Storage RoomAll of the building materials are kept in a whether proof storage room.dozerSep 27, 2011
IMG_3507~0.JPG
Pesticide applicationThis is the pesticide used for termite termination, brand 'kornonam', which mixes with water 1 part to 19 parts. This seems to be a very and simple and effective preventative measure. dozerSep 27, 2011
IMG_3508~0.JPG
Pesticide applicationOK, I never said anything about high tech. This is the pesticide being applied.dozerSep 27, 2011
DSC03069~0.JPG
Color Render ApplicationThere are two layers of render coat applied before the color coat. The render is applied rough and let set up until a finish coat is applied. dozerSep 27, 2011
DSC03069.JPG
Rough Coat RenderThis shows a color coat of render being applied over a dried rough coat render. There is a certain technique which we employed after some initial missteps to get the block outline not to show through to the color coat.dozerSep 27, 2011
IMG_3100.JPG
Blocks being LaidHere the cinder blocks are being laid according to a 'straight' line of fishing wire which is used to keep the rows level.dozerSep 27, 2011
IMG_3103.JPG
6mm Tie-in RebarThis shows a piece of 6mm rebar which sits in between blocks as they are laid and goes through the column framework. This is used to secure the blocks on either side of the column together.dozerSep 27, 2011
IMG_3107.JPG
Wall Section with OpeningsThis shows a section of the perimeter wall, with column openings each 2.5 m. Notice that the columns are always poured after the blocks are laid for better adhesion. dozerSep 27, 2011
IMG_3131.JPG
Pouring a ColumnThe columns are poured after the blocks are laid in place. Here a piece of metal is being used to vibrate the concrete into place within the formwork.dozerSep 27, 2011