IMG_3597.JPG
Safety TankDosch brand 1000 liter safety tank. This type of septic is required in higher population areas. They are a lot of work to install. The are supported by two support columns and a poured foundation. The support is necessary to prevent any settling due to weight.
dozerSep 27, 2011
IMG_3598.JPG
Water Septic #1First dirty water septic tank for the bathroom. Five concrete rings of 1 m x 30 cm are surrounded with large gravel. The gravel layer is about 10 cm thick (all the way around the tank).
dozerSep 27, 2011
IMG_3603.JPG
Safefy Tank PreparationThe safety tank is supported by two support columns and a 15 centimeter footing.
dozerSep 27, 2011
IMG_3606.JPG
The plumbed in safety tank. Note; there is a 1.5" vent exhaust.
dozerSep 27, 2011
IMG_3615.JPG
Toilet PlumbingThe toilet plumbing including an indentation on the ground beam for the venting. Venting of water appliances is often not done here, which leads to sluggish flow out. The vent allows the air to enter and the water to exit.
dozerSep 27, 2011
IMG_3616.JPG
Water Septic #2The deeper second dirty water septic will be about 2 meters deep.
dozerSep 27, 2011
IMG_3778.JPG
Kitchen Drain PipeThe plumbing, like the electric, runs up a designated empty hole of an oversize cinder block. This one is the kitchen drain pipe.
dozerSep 27, 2011
IMG_3829.JPG
This shows two water pipes; a drain and inbound water pipe. There are 5 inbound water pipes (kitchen sink, bathroom sink, toliet, shower, urinal) and 6 outbound (shower drain, bathroom floor drain, urinal, toilet, bathroom sink, kitchen sink). dozerSep 27, 2011
IMG_3830.JPG
Plumbing Entry ExitThis shot shows the 3 plumbing entry/exit areas within their designated over size cinder blocks (1 entry/exit in the forward kitchen, 2 in the bathroom). Also note the vent pipes which will run vertically up through the ceiling, will be tied together, and exit through the roof.
dozerSep 27, 2011
IMG_8780.jpg
Primer Coat of Red OxideEither two coat of primer should be applied or alternatively one coat of primer and another coat of a finish paint. This project we used red oxide primer. dozerSep 27, 2011
IMG_9295.jpg
dozerSep 27, 2011
DSC03165.JPG
Roof TilesLaying roof tiles in place up to the roof valley.dozerSep 27, 2011