Bricks instalmentzappaMar 07, 2009
|
|
|

Steel frames in placezappaMar 07, 2009
|
|

Casting BeamzappaMar 07, 2009
|
|

Casting timezappaMar 07, 2009
|
|

6 March 09'Front view of the roof today with the stacks of blocks for the walls.pklongballMar 06, 2009
|
|

6 March 09'View of the almost completed roof steel and a new stack of Q-Con blockspklongballMar 06, 2009
|
|

6 March 09'Two of the roof crew welding in the small cross-members to the support channels. The square tube will be the support for the roof tile.pklongballMar 06, 2009
|
|

6 March 09'Today the Q-Con blocks were delivered to the site. Total on the truck was 2,000 blocks. The walls will begin soon.pklongballMar 06, 2009
|
|
|

View from house A1 30 meters from the beachzappaMar 05, 2009
|
|
|