June 14The roof structure is almost complete and now the floor can be poured and the roof tile installedpklongballJun 14, 2009
|
|
June 14Underside view of the new stainless gutter installed a few days ago. Now the gutter is primed and ready for the color to match the eavespklongballJun 14, 2009
|
|
June 14Kitchen window frame above the new counter built inpklongballJun 14, 2009
|
|
June 14The master bedroom and office area window framespklongballJun 14, 2009
|
|
June 14This is a view of the pumphouse construction today.pklongballJun 14, 2009
|
|
June 14Today I decided to shoot a few pics of the window frames before the installation of the windows. This is the second bedroom area.pklongballJun 14, 2009
|
|
June 14View of the window frames in living room areapklongballJun 14, 2009
|
|
June 14Here we have today's view into the master bath and the shower zone with the built in bench added for sitting down and enjoying a relaxing shower. A shower unit will be installed near this benchpklongballJun 14, 2009
|
|
June 14Opposite side of the shower zone and the cut out in the wall that will allow storage of any personal items for showeringpklongballJun 14, 2009
|
|
June 12The front as it looks today and the guttering around the eave line. Can you see it?pklongballJun 12, 2009
|
|
June 12We decided to install a rain gutter to the roof line around the read veranda. Huge amounts of rain came off this roof and down the long valley. It is stainless steel and has been painted with a primer so we can match the trim colorpklongballJun 12, 2009
|
|
June 12Just off the balcony the crew added to drain boxes to channel rain water from the roof and the kitchen drain out to the sewer systempklongballJun 12, 2009
|
|