Last additions - Green House Motel |
Bathroom wall tiles.Been trying for several days to get cheap tiles, but the prices seem to have gone up considerably since I built my house. I really wanted white, but I was not prepared to pay 160 baht / m2 or more for the cheapest plain white tiles I could find. I was able to negotiate 123 baht / m2 for 54 m2 of these very light green ones.
It is not necessary to render the walls first.jazzmanMar 20, 2009
|
|
Consumer unitsEach room has its own mini consumer unit with a 32A 2-pole main breaker, a 10A and a 20A MCB. The units cost 500 baht each, fully equipped.
Doing it like this will ensure that if a guest overloads a circuit in the room, only the room breaker(s) will trip and not leave all the rooms in the dark.
The entire building will have a larger consumer unit with an RCCB - of course.
For more details of this and other consumer units, see the Electrical Fittings album.jazzmanMar 20, 2009
|
|
Wall sockets.For more on the motel electrics, see the Electrical Fittings album.jazzmanMar 20, 2009
|
|
Ceiling fan recessPlasterboard (sheetrock) teams do some of the neatest work of all Thai labour.jazzmanMar 20, 2009
|
|
ceiling: suspension: railsA view of the rails partially installed. Some of the electrics still have to be completed.jazzmanMar 20, 2009
|
|
Ceiling suspension: stripsThe rails are suspended from the rafters or tile battens by aluminium strips.jazzmanMar 20, 2009
|
|
Ceiling suspension: clpisThe rails cost 25 baht per 4 m length. One is installed vertically, the other horizontally. The metal clips that hold them together cost 1.20 each.jazzmanMar 20, 2009
|
|
BeforeA clear view of the double C-section ridge beam. Needless to say, all the welds are retouched with red oxide before anything is irreversibly clad or ceilings are closed off.
Our land is L-shaped; today I started negotiating the purchase of the 1/3 rai (about 133 sq. wa, 155 m2) bit in the angle of the L. What a headache - he started off with a price higher than a plot in Pattaya!jazzmanMar 13, 2009
|
|
AfterForeman's own initiative, and I must say, it looks quite neat. I would personally have mitered the fascia boards, but one can't expect everything, and this is a budget build after all.
I finally got the price of the plot of land down to one sixth of the Pattaya price. I still think I paid a bit over the odds, but it's really worth it to have a perfectly rectangular piece of land, and to avoid anyone building near my house.
jazzmanMar 13, 2009
|
|
Plasterboard suspension.A lot opf people on site today, electricians installing the consumer units in the rooms and the fans, and the ceiling men working in all the rooms at the same time. We had also started touching up the welds and scratches on the steel with red oxide, but gave up and started digging footings for the perimeter wall instead.
The materials for the ceiling come to almost exactly 100 baht per square metre.
The complete invoice details have been posted on the forum.jazzmanMar 13, 2009
|
|
Ceiling fansCheap, 48", only 590 baht in GlobalHouse. This one is just spot welded to the beam. It will be taken down again and the tube will be cut to the correct length for suspension in the circular ceiling recess.. The hook will then be securely bolted to the beam and the welds repainted.jazzmanMar 13, 2009
|
|
Day 26 RoofThe roof is almost finished with just a few small snags to tidy up. Remember that there are no drawings for this project and it's a question of make-it-up-as-you-go. It's also a training excercise for my workers. We still have a lot to do on the land including a frontage wall with gate and motel gatehouse at one end, and another gate with archway at the other end of the land, a large sala as a dining-room restaurant, a floating sala on the pond, and a meeting room/classroom on the field behind.jazzmanMar 09, 2009
|
|