Home > House Construction > Cool Thai House Phase 2 > Structure

Last additions - Structure
IMG_1961.jpg
Poured Ring BeamA poured ring beam with U shaped rebar to keep it in place. This is in a section that used 20 cm. thick wall. 1 commentsdozerSep 26, 2011
IMG_1953.jpg
15 cm BlocksThere was an area of the house which required 20 cm wide blocks but unfortunately we had ordered 15 cm wide blocks. Here I am figuring out that you can use the 15 cm block anyway if you lay them on their side because all variations of block sizes are always 20 cm high (duh!!). dozerSep 26, 2011
IMG_1940.jpg
Form Work for Ring BeamThe formwork for a ring beam on top of a 7.5 cm section of walling for a storage room. dozerSep 26, 2011
IMG_1926.jpg
Laying BlocksPreparing the hole in the column for the 6mm rebar to be placed and protrude into the block adjacent to the column.dozerSep 26, 2011
IMG_1924.jpg
AdhesiveA adhesive is used to fix the horizontal pieces of 6 mm rebar in the column. This rebar is fitted into holes drilled into the column and it extends into the first block next to the column to avoid separation problems. dozerSep 26, 2011
IMG_1918.jpg
Aerated BlocksThe q con aerated blocks are glued into place. Each row is attached to the column with 6 mm rebar. dozerSep 26, 2011
IMG_1913.jpg
Level LayerA level layer of cement mixed with sand is laid to ensure the block laying start on a level surface. Notice the clear leveling line. It is never assumed that the floor is perfectly level. dozerSep 26, 2011
IMG_1904.jpg
Column Being Topped UpThis column is being topped up with Lanko 701 grout placed into formwork because the original poured height was too low. (oops!!)dozerSep 26, 2011
IMG_1899.jpg
Lanko 701This is a high compressive strength non shrink grout which was used to top up any columns that were poured to an incorrect height.dozerSep 26, 2011
IMG_1873.jpg
Walkway on Top of SepticHere the walkway is being poured behind the house. dozerSep 26, 2011
IMG_1863.jpg
Crack VoidA slight crack/void in a column probably due to inadequate vibration. Some small voids like this are OK as long as their aren't too many. dozerSep 26, 2011
IMG_1860.jpg
Metal SpacerA metal spacer is in place to set the position of the rebar during the walkway pour. It is good to use spacers in confined areas like this one which will not need to be walked on.dozerSep 26, 2011