100_0227.JPG
Brickwork started - this will eventually become the main bedroom.Thaifu TMar 05, 2007
100_0226.JPG
Upper columns ready for concrete. Still using the metal shuttering. Plenty of bagged cement has been delivered ready to start the brickwork.Thaifu TMar 05, 2007
100_0210.JPG
Pouring the first floor; now back to the tried and trusted method - handballing. Steel work for the upper columns alreaedy started.Thaifu TMar 05, 2007
100_0209.JPG
Getting ready for the first floor concrete. Steel re-inforcing being laid over the slabs.Thaifu TMar 05, 2007
100_0206.JPG
Preparing the first floor. Precast re-inforced concrete slabs are laid across the beams.Thaifu TMar 05, 2007
100_0202.JPG
Pouring the beams (2). Greater accuracy is achieved using the tube slung below the bucket. The flow is still controlled by the 'jockey'.Thaifu TMar 04, 2007
100_0201.JPG
Pouring the beams (1). CPAC deliver the concrete and pour into the bucket; hoisted by crane; then the 'jockey' releases the concrete at the appropriate moment.Thaifu TMar 04, 2007
100_0171.JPG
My first view on arriving from the UK. Concrete base laid; steel work for columns started; metal shuttering delivered. Note the 'good luck' artefacts hanging from the columns following the usual 'blessing' by the monksThaifu TMar 04, 2007
100_0200.JPG
'Hotel California' Some of the workers lived here during the whole construction phase. Actually this helps with site security at night. Later the 'hotel' was doubled in size to accommodate more workers.Thaifu TMar 04, 2007
100_0199.JPG
Doing the shuttering for the beams. Wish my football team had as much supportThaifu TMar 04, 2007
100_0193.JPG
All columns finished, they are clad in 'cling film', I presume to assist the curing process. Now working on the steel work for the beamsThaifu TMar 04, 2007
100_0179.JPG
Metal shuttering going up for columns. In the foreground, metal supports to be used for doing the beams.Thaifu TMar 03, 2007