Week 8 - Groundfloor pour and finish upper ringbeams
|
|
|
|

Starting Concrete Pour from the backUtility Room, Kitchen, hallway , balconey to rightchangnoi
|
|

Starting the Ground floor pour from the backMum bedroom, ensuite, hallway and GF balconey to rightchangnoi
|
|

Starting the Ground floor pour from the backMums bedroom and ensuite areachangnoi
|
|
|

Prep for Concrete PourThis view shows the prep going on prior to the pour of concrete and shows where the balconey will be on the side of the house. This area along with all bathrooms will be poured seperately as it will be lower than the ground floor with a slight slope for water drainage.changnoi
|
|

Groundfloor CastThis was the day after the concrete pour and already hard so started building wallschangnoi
|
|
|

Prep for downstairs WCThis shows the pipework installed prior to the concrete pourchangnoi
|
|

Ground floor WC after concrete pourchangnoi
|
|

View of whole groundfloor after concrete pourThis shows the groundfloor after the pour from the back to the front on the right where the wc will bechangnoi
|
|

Mums Ensuite before Concrete Pourchangnoi
|
|
|

|
|
|