by AussieBoy » Mon Aug 11, 2008 4:35 pm
As they say piles are as good as the reo steel they put into them, you would want to see the size and number of steel being put into each pile, and the difference between companies.
A 300 dia bored pier will consume 0.070m3 concrete and use 4mts x 10mm reo bars and 3 x 6mm a ligitures to tie the steel together to make a cage 200x200
Costing would be .070 concrete @1600bt m3 = 112 bt
Steel reo 10mm 200bt 10mt = 20bt mt
ties 6 mm @ 100bt 10mt = 30btmt
labour 5mt cage per hour = 30 bt
tie wire = 10 bt
labour insert cage into
hole & supervise =100
total cost mt to fill bored pier 300bt mt depending on material cost
Machine cost Ex Udon 1,250B / hour bored 6 holes 5 mt deep in 90min set up and travel cost 1 hour
total cost 6 holes 3,200B
Cost per 5 mt bored pier filled with concrete and steel placement labour including
2100b per pier
420 B mt
Soil condition dry stiff hard clay top, sticky clay at 1 mt and below
for larger bored pied do the sums, bigger diameter less depth, as the truck mounted borer could only go 5 mt if you wanted more loadings on each pier you go bigger diameter, more friction on side of pier, some will be designed to bear on the pier end, meaning boring till you hit something firm.
BKK 20-30mt piles for large buildings are very common, drilling through the swamp of this type of material the bored pier would collasp on it self, in general bored pires are cheaper in OZ, if the soil will stand up to maintaining support of the pier long enough to be filled with concrete, if the ground is wet and soggy piling is the only option
What did it cost for the piles to be driven in? for 250x250 x 6mt with no breakages 400B mt (from the original posters quote supplied)
Not much difference in cost between driven or bored piers